WSHT Mining Group
WSHT Mining Group
EPC Case Study · Project Case Studies

1,200 TPD Iron Ore Processing Circuit — Africa

Complete beneficiation line including three-stage crushing, rod & ball milling, and multi-stage magnetic separation producing 65% Fe high-grade iron concentrate for an African iron ore operation.

Global
2025
Project Case Studies
2,000+ Tons / Day Capacity
30+ Equipment Units
12 Months Delivery

Project Background

An East African iron ore miner needed to upgrade low-grade hematite-magnetite ore (32% Fe head grade) into a saleable 65% Fe concentrate for the regional steel industry. The site has no grid power, so the plant had to be designed for diesel generator operation with optimized power consumption.

Process Design

WSHT developed a flowsheet combining magnetic separation at coarse and fine sizes:

  • Three-stage crushing: jaw + cone + HPGR (high pressure grinding rolls) reducing to -3mm
  • Wet rod milling in open circuit, then ball milling in closed circuit (P80 = 80μm)
  • Stage 1: low-intensity magnetic separation (LIMS) on rod mill discharge
  • Stage 2 & 3: LIMS on ball mill cyclone underflow and final concentrate cleaning
  • Tailings thickening & water recovery circuit

Equipment Supplied

Complete crushing & grinding package: C130 jaw crusher, GP220 cone crusher, two Polycom HPGR rolls, MBZ2136 rod mill, MQG2700×4500 ball mill, 6 magnetic separators, 4 thickeners, full pumping and pipeline network.

Civil, Power & Installation

Project included 8,000 m² of concrete works, 2,400 t of steel, a 6 MW diesel power plant, and a 35 km raw water pipeline from a nearby river. Installation completed by a 90-person WSHT site team in 7 months.

Performance & Results

Plant ramped up to design throughput within 4 weeks of commissioning. Final concentrate grade 65.3% Fe at 82% mass recovery, exceeding the client's target. Power consumption 18% below the original design estimate.

Project Highlights

Efficient Delivery

Completed 30 days ahead of schedule with zero safety incidents during 1,200+ construction days.

Over-Performance

Plant capacity exceeds design specification by 15%, achieving 3,000 tpd within first 3 months.

Environmental Compliance

Full compliance with international environmental standards including ISO 14001 certification.

Client Satisfaction

5-year O&M contract extension signed — a testament to our delivery quality and support.

Have a Similar Project in Mind?

Our EPC team has delivered 500+ mining projects worldwide. Tell us about your project — we'll respond within 48 hours.

Project Info

  • Project ID WSHT-EPC-0145
  • Location Global
  • Mineral Type Project Case Studies
  • Year Completed 2025
  • Design Capacity 2,000+ tpd
  • Delivery Time 12 Months
  • Equipment Count 30+ Units
  • Project Scope Full EPC + O&M

EPC Project Hotline

+86 135 2500 5907

Speak with our senior EPC engineer today. Free consultation and site assessment.

START YOUR EPC PROJECT

From Concept to Commissioning — One Partner, One Promise.

Tell us about your ore body, target capacity and project location. Our EPC team will respond with a tailored proposal within 48 hours.

EPC Hotline +86 135 2500 5907
Project Email contact@wshtmining.com