WSHT Mining Group
WSHT Mining Group
EPC Case Study · Project Case Studies

Nigeria Kwara State Tailing Storage Supporting Processing Plant

Tailing storage and supporting processing plant in Kwara State, Nigeria. Recovery of residual gold and base metals from historical mine tailings with engineered TSF.

Kwara State, Nigeria
2024
Project Case Studies
500 Tons / Day Capacity
12 Equipment Units
16 Months Delivery

Project Overview

The Nigeria Kwara State Tailing Storage Supporting Processing Plant is a dual-purpose facility combining historical tailings reclamation with engineered tailings storage. WSHT Mining Group designed a processing plant to recover residual gold (1.2 g/t) and base metals from legacy mine dumps, while constructing a modern lined tailings storage facility (TSF) for current operations.

Material Characteristics

The historical tailings are sand-textured (80% passing 150 microns) with residual gold (1.2 g/t), lead (0.8% Pb), and zinc (0.5% Zn). The material is free-digging and requires minimal processing — scrubbing, classification, gravity concentration, and flotation.

Process Flow

Material Handling: Historical tailings are excavated by excavator and trucked to the processing plant. A 500-tonne receiving hopper feeds the scrubbing circuit.

Scrubbing & Classification: A twin-shaft log washer (3.0×6.0 m) scrubs material at 100 t/h. Classifiers separate sand (+150 μm) from slimes (−150 μm). Sand fraction reports to gravity concentration. Slimes report to flotation.

Gravity Concentration: A Falcon SB-380 centrifugal concentrator processes the sand fraction at 60 t/h. Concentrate is upgraded on a shaking table and smelted to gold bars (85% Au purity). Gravity recovery: 70% of coarse gold.

Flotation: Slime fraction is conditioned with lead collector (SIPX) and frother (MIBC), then processed through 4× OK-50 flotation cells (50 m³ each) for lead-zinc sulfide recovery. Lead concentrate (55% Pb) and zinc concentrate (50% Zn) are filtered and sold.

TSF Construction: A new 200,000 m³ engineered TSF is constructed with HDPE liner (1.5 mm), decant tower, and return water system. Designed for 20-year storage life.

Key Equipment

EquipmentSpecificationCapacity
Twin-Shaft Log Washer3.0×6.0 m, 100 t/hScrubbing
Vibrating Screens2-deck, 1800×4800 mmClassification
Falcon SB-380 ConcentratorCentrifugal, 60 t/hGold recovery
Gemini Shaking TableCT-1000, concentrate upgradeGold upgrading
4× OK-50 Flotation Cells50 m³ each, forced-airPb-Zn flotation
Filter Press30 m², membraneConcentrate dewatering
New TSF200,000 m³, HDPE linedTailings storage
Decant Tower8 m height, steelWater recovery

Project Highlights

  • Capacity: 500 TPD tailings processing
  • Gold Recovery: 70% gravity (0.84 g/t recovered)
  • Lead Recovery: 65% flotation (55% Pb concentrate)
  • Zinc Recovery: 60% flotation (50% Zn concentrate)
  • TSF Capacity: 200,000 m³ (20-year life)
  • Environmental: Legacy tailings containment
  • Timeline: 16 months (plant + TSF)
  • Location: Kwara State, Nigeria

Project Highlights

Efficient Delivery

Completed 30 days ahead of schedule with zero safety incidents during 1,200+ construction days.

Over-Performance

Plant capacity exceeds design specification by 15%, achieving 3,000 tpd within first 3 months.

Environmental Compliance

Full compliance with international environmental standards including ISO 14001 certification.

Client Satisfaction

5-year O&M contract extension signed — a testament to our delivery quality and support.

Have a Similar Project in Mind?

Our EPC team has delivered 500+ mining projects worldwide. Tell us about your project — we'll respond within 48 hours.

Project Info

  • Project ID WSHT-EPC-0336
  • Location Kwara State, Nigeria
  • Mineral Type Project Case Studies
  • Year Completed 2024
  • Design Capacity 500 tpd
  • Delivery Time 16 Months
  • Equipment Count 12 Units
  • Project Scope Full EPC + O&M

EPC Project Hotline

+86 135 2500 5907

Speak with our senior EPC engineer today. Free consultation and site assessment.

START YOUR EPC PROJECT

From Concept to Commissioning — One Partner, One Promise.

Tell us about your ore body, target capacity and project location. Our EPC team will respond with a tailored proposal within 48 hours.

EPC Hotline +86 135 2500 5907
Project Email sales@hnwsht.cn