WSHT Mining Group
WSHT Mining Group
EPC Case Study · Project Case Studies

Republic of South Africa Johannesburg Crushing & Mineral Processing Complex

Integrated crushing, grinding, and CIL gold processing complex in Johannesburg, South Africa. The facility processes 3,000 TPD gold-bearing ore through three-stage crushing, SAG/ball milling, and eight-stage carbon-in-leach circuit.

Johannesburg, South Africa
2024
Project Case Studies
3,000 Tons / Day Capacity
35 Equipment Units
24 Months Delivery

Project Overview

The Johannesburg Crushing & Mineral Processing Complex is a brownfield expansion project converting a former gold mine into a modern CIL processing facility. WSHT Mining Group designed and supplied the complete comminution and leach circuit for processing 3,000 TPD of underground gold ore from the Witwatersrand Basin.

Ore Characteristics

The Witwatersrand gold ore is quartzite-hosted with fine-grained gold particles (average 4.5 g/t Au) disseminated through pyritic reef units. The ore is competent (UCS 180-220 MPa) and requires aggressive grinding to liberate the fine gold from the siliceous gangue. Bond Ball Mill Work Index: 16.2 kWh/t.

Process Flow

Crushing: Underground ore is tip-loaded to a 200-tonne receiving bin. A vibrating grizzly feeder scalps fines to bypass the C160 jaw crusher (primary, 400-800 t/h). Secondary and tertiary crushing is performed by two HP800 Symons cone crushers in series, producing a P80 = 10 mm product at 150 t/h.

Grinding: A Φ6.2×2.5 m SAG mill (4,500 kW, gearless drive) operates in closed circuit with a vibrating screen, reducing product to P80 = 2 mm. Two Φ4.0×6.0 m ball mills (each 2,200 kW) grind to 80% passing 75 microns in closed circuit with hydrocyclone clusters. Combined grinding power: 8,900 kW.

CIL Circuit: Ground slurry is thickened to 50% solids and pumped through 8 CIL tanks (6.0 m diameter × 6.5 m height, 185 m³ each). Cyanide concentration is maintained at 200-300 ppm NaCN at pH 10.5 (lime dosing). Total leach residence time: 36 hours. Activated carbon (24×48 mesh coconut shell) is loaded at 15 g/L and advanced counter-current to the slurry flow.

Gold Recovery: Loaded carbon is stripped in a Zadra elution circuit at 110°C and 1% NaCN/NaOH solution. Gold is recovered by electrowinning on stainless steel cathodes and smelted to doré bars (98.5% Au, 1.2% Ag). Strip efficiency: 99.5% in 6 stages.

Key Equipment

EquipmentSpecificationCapacity
C160 Jaw Crusher1600×1200 mm feed opening400-800 t/h
2× HP800 Cone CrushersSecondary + tertiary200-400 t/h each
Φ6.2×2.5 m SAG Mill4,500 kW, gearless drive150 t/h
2× Φ4.0×6.0 m Ball Mills2,200 kW each120 t/h each
8× CIL Tanks6.0 m dia × 6.5 m, 185 m³36 h residence
Zadra Elution Circuit3-stage, 110°C20 t carbon
Electrowinning Cell Bank48 cathodes, stainless steel150 kg Au/day
Induction Furnace500 kg capacityDoré production

Project Highlights

  • Capacity: 3,000 TPD (900,000 TPA) gold ore
  • Gold Recovery: 94-96% CIL recovery
  • Concentrate: Doré bars 98.5% Au purity
  • Power: 12 MW installed, 8.5 MW average
  • Water: 70% recycling, 1.8 m³/t ore
  • Staffing: 120 operational personnel
  • Timeline: 24 months EPC delivery
  • Location: Johannesburg, Gauteng, South Africa

Project Highlights

Efficient Delivery

Completed 30 days ahead of schedule with zero safety incidents during 1,200+ construction days.

Over-Performance

Plant capacity exceeds design specification by 15%, achieving 3,000 tpd within first 3 months.

Environmental Compliance

Full compliance with international environmental standards including ISO 14001 certification.

Client Satisfaction

5-year O&M contract extension signed — a testament to our delivery quality and support.

Have a Similar Project in Mind?

Our EPC team has delivered 500+ mining projects worldwide. Tell us about your project — we'll respond within 48 hours.

Project Info

  • Project ID WSHT-EPC-0330
  • Location Johannesburg, South Africa
  • Mineral Type Project Case Studies
  • Year Completed 2024
  • Design Capacity 3,000 tpd
  • Delivery Time 24 Months
  • Equipment Count 35 Units
  • Project Scope Full EPC + O&M

EPC Project Hotline

+86 135 2500 5907

Speak with our senior EPC engineer today. Free consultation and site assessment.

START YOUR EPC PROJECT

From Concept to Commissioning — One Partner, One Promise.

Tell us about your ore body, target capacity and project location. Our EPC team will respond with a tailored proposal within 48 hours.

EPC Hotline +86 135 2500 5907
Project Email sales@hnwsht.cn