Kyrgyzstan Talas Oblast Flotation Concentrator Plant

Complete EPC flotation concentrator in Talas Oblast, Kyrgyzstan processing polymetallic copper-zinc-gold ore into marketable concentrates. WSHT delivered crushing, grinding, sequential flotation, concentrate dewatering, and tailings management circuits.

Talas Oblast, Kyrgyzstan
2025
Project Case Studies
2,000 Tons / Day Capacity
28 Equipment Units
18 Months Delivery

Project Overview

The Kyrgyzstan Talas Oblast Flotation Concentrator is a greenfield EPC project processing polymetallic sulfide ore containing copper (1.2% Cu), zinc (2.8% Zn), and gold (0.8 g/t Au). WSHT Mining Group delivered the complete mineral processing facility from ROM ore reception through to final concentrate filtration and dispatch.

Ore Characteristics

The deposit is a volcanogenic massive sulfide (VMS) type with chalcopyrite, sphalerite, and pyrite as the principal ore minerals. The ore has a Bond Work Index of 14.5 kWh/t (medium-hard) and requires fine grinding to 80% passing 45 microns for optimal mineral liberation. The sequential flotation circuit separates copper, zinc, and pyrite concentrates in a differential flotation arrangement.

Process Flow

Crushing: ROM ore (P80 = 800 mm) is reduced to P80 = 10 mm through a three-stage crushing circuit comprising a C140 jaw crusher (primary), two HP500 cone crushers (secondary and tertiary), and a 3YK-2460 vibrating screen for closed-circuit classification. Total crushing capacity: 250 t/h.

Grinding: The crushing product is stored in a 5,000-tonne live stockpile, then metered to a Φ4.0×6.0 m overflow ball mill (2,200 kW) operating in closed circuit with a cluster of 8× NX350 hydrocyclones. Target grind: 80% passing 45 microns. The mill processes 120 t/h at 65% solids density.

Flotation: Ground slurry is conditioned with sodium isopropyl xanthate (collector) and methyl isobutyl carbinol (MIBC frother) before entering the sequential flotation circuit. The rougher circuit consists of 8× OK-160 forced-air flotation cells (160 m³ each) providing 30 minutes residence time. Copper is selectively floated first, followed by zinc activation with copper sulfate and subsequent zinc flotation. Pyrite is recovered in the scavenger circuit.

Concentrate Handling: Copper concentrate (28% Cu) and zinc concentrate (55% Zn) are separately thickened in 15 m diameter high-rate thickeners, then dewatered on 60 m² pressure filters to 9% moisture. Concentrates are stored in separate covered bins before dispatch by truck.

Key Equipment

EquipmentSpecificationCapacity
C140 Jaw Crusher1400×1060 mm feed opening250-400 t/h
2× HP500 Cone CrushersMedium and fine crushing150-300 t/h each
3YK-2460 Vibrating Screen3-deck, 2400×6000 mm200-400 t/h
Φ4.0×6.0 m Ball Mill2,200 kW, rubber liners120 t/h
8× NX350 HydrocyclonesClassification cluster120 t/h total
8× OK-160 Flotation CellsForced-air, 160 m³ each1,280 m³ rougher
2× 15m ThickenersHigh-rate, paste discharge80 t/h each
2× 60m² Pressure FiltersMembrane type40 t/h each

Project Highlights

  • Capacity: 2,000 TPD (600,000 TPA) polymetallic ore
  • Copper Concentrate: 28% Cu grade, 92% recovery
  • Zinc Concentrate: 55% Zn grade, 87% recovery
  • Gold Recovery: 78% into copper concentrate
  • Water Recycling: 85% process water recycled
  • Power: 8 MW connected load, 5.5 MW average
  • Timeline: 18 months EPC delivery
  • Location: Talas Oblast, Kyrgyzstan

Project Highlights

Efficient Delivery

Completed 30 days ahead of schedule with zero safety incidents during 1,200+ construction days.

Over-Performance

Plant capacity exceeds design specification by 15%, achieving 3,000 tpd within first 3 months.

Environmental Compliance

Full compliance with international environmental standards including ISO 14001 certification.

Client Satisfaction

5-year O&M contract extension signed — a testament to our delivery quality and support.

Have a Similar Project in Mind?

Our EPC team has delivered 500+ mining projects worldwide. Tell us about your project — we'll respond within 48 hours.

Project Info

  • Project ID WSHT-EPC-0329
  • Location Talas Oblast, Kyrgyzstan
  • Mineral Type Project Case Studies
  • Year Completed 2025
  • Design Capacity 2,000 tpd
  • Delivery Time 18 Months
  • Equipment Count 28 Units
  • Project Scope Full EPC + O&M

EPC Project Hotline

+86 135 2500 5907

Speak with our senior EPC engineer today. Free consultation and site assessment.

START YOUR EPC PROJECT

From Concept to Commissioning — One Partner, One Promise.