How Long Does It Take to Build a Mining Processing Plant?

Answers to common questions about mining plant construction timelines, from small portable plants to large-scale EPC projects, including factors that affect project duration.

WSHT Mining Group
Senior Mining Engineer
· 2026-06-24 · 1 min read
Share

Mining Plant Construction Timelines

One of the most common questions in mining project development is "how long will it take to build?" The answer depends on project size, complexity, location and delivery method.

Small Portable Plants

Capacity: Under 200 tph

  • Equipment manufacturing: 8-12 weeks
  • Site preparation: 4-6 weeks
  • Installation and commissioning: 4-8 weeks
  • Total: 4-7 months

Medium Stationary Plants

Capacity: 200-500 tph

  • Engineering: 8-16 weeks
  • Equipment manufacturing: 12-20 weeks
  • Site preparation: 8-12 weeks
  • Installation and commissioning: 12-20 weeks
  • Total: 10-18 months
Mining Plant Construction Timeline

Mining Plant Construction Timeline

Large EPC Projects

Capacity: 500+ tph or complex circuits

  • FEED and engineering: 16-24 weeks
  • Equipment manufacturing: 20-30 weeks
  • Civil works: 12-20 weeks
  • Installation and commissioning: 20-30 weeks
  • Total: 15-26 months

Factors Affecting Timeline

  • Project complexity and circuit design
  • Site conditions and location
  • Permitting and approvals
  • Infrastructure availability
  • Equipment availability
  • Labor availability

WSHT provides detailed project schedules with every proposal, accounting for your specific requirements and location.

Written by

WSHT Mining Group

WSHT Mining Editorial Team consists of senior mining engineers, metallurgical experts and industry analysts with 15+ years of on-site experience in crushing, screening, grinding and flotation circuits worldwide.