WSHT Mining Group
WSHT Mining Group
Mining Project Cases

Cabral Gold 85% Complete at Cuiú Cuiú Heap Leach — First Gold Pour Q4 2026

Cuiú Cuiú Gold-in-Oxide Heap Leach Project Commissioning Update Cabral Gold Inc. (TSXV: CBR) has reached a major construction milestone at its Phase 1 gold-in-oxide heap leach project in the Cuiú...

Flora
Editorial Team
· 2026-07-09 · 2 min read
Share

Cuiú Cuiú Gold-in-Oxide Heap Leach Project Commissioning Update

Cabral Gold Inc. (TSXV: CBR) has reached a major construction milestone at its Phase 1 gold-in-oxide heap leach project in the Cuiú Cuiú Gold District, northern Brazil. As of July 2026, the project is approximately 85% complete with over 90% of project costs committed under contract, and commissioning is actively underway.

Construction Progress

The dry circuit construction is complete, and the project has achieved several critical milestones:

  • Mining commenced: Ore from the MG orebody is being processed through the sizer, agglomerated, and transported by conveyor to heap leach pads
  • Water management: Water collection and management ponds are fully constructed
  • Heap leach pads: Pad construction well underway, with pad 2 of four to be completed in July
  • ADR plant: The adsorption-desorption-recovery plant has arrived in Brazil and is expected on site late July 2026
  • Safety record: 501,743 total hours worked in 2026 with zero lost time incidents

Processing Design

The Cuiú Cuiú heap leach operation is designed around a simple, low-cost processing route requiring no crushing or grinding:

  • Feed rate: 3,000 tonnes per day of near-surface gold-in-oxide saprolite
  • Free digging: Material requires no drilling or blasting, significantly reducing mining costs
  • Gold recovery: Column leach tests returned 72.5%–96% recovery; 88% assumed for the PFS
  • Production target: ~25,000 oz/year during initial years, 113,155 oz total over 6.2-year mine life

Project Economics

The July 2025 Pre-Feasibility Study confirms highly attractive project economics:

  • After-tax IRR: 78% at US$2,500/oz gold base case
  • NPV(5%): US$73.9 million
  • Capex: US$37.7 million (fully funded via US$45M gold loan)
  • AISC: US$1,210/oz; Cash costs US$950/oz during initial years
  • Payback period: Just 10 months

Resource Base

The Cuiú Cuiú district hosts substantial NI 43-101 compliant resources across three main gold deposits: Indicated resources of 12.29Mt @ 1.14 g/t gold (450,200 oz) in fresh material and 13.56Mt @ 0.50 g/t gold (216,182 oz) in oxide, plus Inferred resources of 13.63Mt @ 1.04 g/t gold (455,100 oz) in fresh and 6.4Mt @ 0.34 g/t gold (70,569 oz) in oxide.

Next Steps

Key milestones ahead include ADR plant installation (late July), wet circuit commissioning during Q3 2026, and commercial production and ramp-up in Q4 2026. Cash flow from Stage 1 will fund expansion and a PEA on the larger hard rock resource (Stage 2) planned for 2027.

Written by

Flora

Henan WanshiHengtong Intelligent Equipment Co., Ltd is a professional Chinese manufacturer and global supplier of complete mining & mineral processing machinery, integrating independent R&D, production, overseas sales and full EPC+O&M mine project service. We specialize in manufacturing jaw crushers, hammer crushers, shaking tables, wet pan mills, centrifugal concentrators and full gold processing assembly lines, serving small & medium gold mines, quarry plants and mineral separation projects across the world. Our factory owns standardized production workshops, strict raw material inspection and finished product testing systems, all machines pass international quality standards for long service life and stable running performance. With rich overseas project experience, we have exported our mining equipment to India, Ghana, DRC, Mali, Philippines, Indonesia and over 40 countries. Our professional technical team can customize ore processing flow layout, equipment configuration and on-site installation guidance according to your ore condition, hourly output and local site environment. We adhere to factory-direct sales model without middlemen, offering competitive factory price, timely delivery and lifelong after-sales technical support. Whether you need single crushing machine or a full set of gold recovery beneficiation plant, we provide one-stop mining solution for all global mine investors and equipment importers. For product catalog, technical parameters and customized mine design, please contact us via WhatsApp: +86 15560175572

Looking for a reliable mining equipment partner? Let's Talk.

Global EPC project delivery, custom configuration and 24/7 after-sales support worldwide.